Monday, October 13, 2014

Mountain's Edge Area County Roadwork Update


http://theknisleygroup.blogspot.com/2014/10/mountains-edge-area-county-roadwork.html


County Roadwork Update In Mountain's Edge Area


The following is the update provided by the County: Planned Projects


Pave additional northbound lane at Buffalo and Mountain’s Edge Parkway – Anticipate work to be underway by end of Nov/Dec 2014.

Light at Buffalo and Mountain’s Edge Parkway – On the design list with construction 2015 but right-of-way needs on the southeast corner may delay construction. Anticipate advertising for construction late summer/fall 2015 if the right-of-way is acquired in time.

Cactus 6 lanes west from Jones to Rainbow – Construction of 4 lanes on Cactus Ave, Rainbow to Verona Wood (bridge over Union Pacific Railroad) – substantial completion December 2014. Traffic signal at Cactus and Jones anticipate advertising for construction October 2014.

4.      Pave Rainbow south from Cactus to Erie – Work included with Cactus/Union Pacific Railroad project. Substantial completion December 2014

5.      Pedestrian Crossing at Buffalo and Gomer near park – Plans are 60% and project will include pedestrian activated flasher and median modifications to allow left turns into Exploration Park. It is anticipated to advertise for construction Jan/Feb 2015.

6.      Transition travel lanes on Gomer between Durango and Buffalo to bike/park lanes – County will review removing a travel lane to provide bicycle/parking lane with buffer.

7.      Pave additional northbound lane at Durango and Blue Diamond 1 thru lane, 1 right turn lane – The County will apply for NDOT permit to do the work, construction schedule dependent on approved permit but is scheduled to start end of Oct/Nov 2014. Plan is to pave 2 additional lanes for a total of 4 lanes: 1 left, 2 thru, 1 right turn only.

8.     Pave Durango 6 lanes north of Blue Diamond to 215 – (SID) Construct Durango Drive to 4 thru lanes between Blue Diamond and Windmill. Anticipate advertising for construction Fall of 2015.

9.      Pave Rainbow north from Cactus to Blue Diamond – Anticipate advertising for construction spring/summer of 2015.

10. Light proposed for Blue Diamond and El Capitan- A traffic study is being conducted by NDOT. 

11.   Light proposed at Blue Diamond and Fort Apache – Following up with NDOT on outcome of traffic study and design/construction schedule.

·           There are no plans at this time to connect Fort Apache Road and Blue Diamond South.

·         “Complete streets”) on Cactus Bridge – There will be sidewalks and the County is reviewing a striping plan to include a shoulder line that bicyclists may use (3-ft law). Bike/Pedestrian Bridge planned at Erie Avenue over UPRR-est 2016-2017

·         Request for review of traffic signal coordination on Blue Diamond during AM/PM peaks – The issue has been referred to the Regional Transportation Commission.

·         For parents transporting students to Tarkanian Middle School –The County is paving Lindell between Pyle and Frias to provide additional access to Cactus Avenue.

·         The commercial area on the corner of Blue Diamond and Buffalo is in escrow. If all goes as planned, construction may start as early as first quarter 2015.






Content From Mountain's Edge Master Association Newsletter
Written By Nickel Lowman 
The Knisley Group 
Keller Williams Realty Southwest Las Vegas 
www.TheKnisleyGroup.com